Progress on the PF1 poloidal field magnet

发布时间:2014-9-12 16:46 原作者:Alexander Petrov, ITER Russia   来自: ITER newsline

In an important manufacturing milestone for Russia and Europe, the first two 414-metre production lengths of conductor for poloidal field magnet #1 (PF1) have been successfully manufactured.

On 5 August and 3 September, poloidal field cable manufactured in Russia underwent all of the phases of jacketing and compaction at the Criotec facility in Italy. Destined for spooling into the PF1 magnet, the jacketed conductor will be returned after necessary tests to the Efremov Institute in Saint Petersburg, where magnet manufacturing will take place. Criotec specialists have already begun welding activities on the metal jacket of a third conductor length for Russia prior to its compaction.

 

At Criotec (Italy), jacketing and compaction were carried out on the first two production lengths of poloidal field cable for poloidal field magnet #1 (PF1).

This cross-border cooperation is part of a Procurement Implementation Agreement signed between Europe and Russia that stipulates that the Russia will manufacture the niobium-titanium (NbTi) superconducting strand and cables for both the Russian and European poloidal field conductor lengths (26 lengths for Russia and 10 for Europe), while Europe will jacket both the Russian and European poloidal field cables.

In compliance with procedure, qualification samples were cut from both jacketed lengths for testing at the SULTAN facility (CRPP, Switzerland). Testing of the first qualification sample is planned for November 2014. 

The first poloidal field conductor length for PF1 has already passed final tests in the vacuum chamber. The conductor will be delivered to the Efremov Institute by the end of 2014, where spooling activities for the first double pancake will start in 2015. Russia will complete the poloidal field conductors for PF1 by the end of 2016. 

上一篇:A protected view of the plasma for ITER diagnostics下一篇:Europe signs contracts for blanket first wall prototypes

推荐阅读
又一核电机组开工!
又一核电机组开工!
4月26日11时56分,国家电投广东廉江核电项目一期工程2
12个!又一“核电大省”披露重点项目名单
12个!又一“核电大省”披露重点项目名单
“核电大省”广东日前发布广东省2024年重点建设项目计
刚刚!又一台核电机组首次并网成功
刚刚!又一台核电机组首次并网成功
4月9日20时29分,中广核广西防城港核电站4号机组首次
中国广核披露一季度发电量及11台核电机组建设情况!
中国广核披露一季度发电量及11台核电机组建
4月9日,中国广核披露2024年第一季度运营情况。2024年
首届核能峰会举行,核能复兴开始……了吗?
首届核能峰会举行,核能复兴开始……了吗?
3月21日,首届核能峰会在比利时首都布鲁塞尔举行,会
我国在建核电机组 26 台,保持全球第一
我国在建核电机组 26 台,保持全球第一
近年来,中国核电产业迎来了重启后的审批和建设高潮。
精彩图片
  • 又一核电机组开工!
  • 12个!又一“核电大省”披露重点项目名单
  • 刚刚!又一台核电机组首次并网成功
  • 中国广核披露一季度发电量及11台核电机组建设情况!
    关注我们
  • 微信公众号:
  • NuclearNet
  • 扫描二维码加关注

Powered by Discuz! X3.2 © 2001-2013 Comsenz Inc.

联系我们|网站声明|中国核网-核能领域第一垂直门户网站