Design phase concludes for ITER rectangular bellows

发布时间:2014-9-19 13:59 原作者:Igor Sekachev, Cryostat and VVPSS Section   来自: ITER newsline

Testing has ended on a full-scale, rectangular bellows prototype at the Swiss firm Kompaflex (kompaflex ag), successfully completing the last step in the bellows design.

Eighty-five large, rectangular bellows will be used between the ITER vacuum vessel, the cryostat and the walls of the Tokamak Building themselves to isolate the ultra-high vacuum inside the cryostat from the building port cell environment, and to compensate relative movement that can occur during different operational regimes  like baking of the vacuum vessel, or during seismic events.

On 27 August, a 3.2 x 3.6 metre prototype of the upper port duct bellows successfully passed pressure stability tests. Even in the case of the largest required pressure of 0.6.bar across the bellows—only predictable elastic deformation of the bellows was caused and following pressure relief, the bellow convolutions returned to their initial position. Only at 1bar pressure across the bellows the first small plastic deformations of 2mm were detected, which showed significant design margin to the pressure requirements.

 

At the Swiss firm Kompaflex, where the water pressure test on the full-size rectangular bellows prototype was successfully carried out: Guillaume Vitupier and Igor Sekachev from ITER (front row) and the Kompaflex team: Werner Löhrer, CEO (centre); Remo Hribernigg, project leader; Bairush Ajeti, expediting; Antonio Coelho Soares, certified welder; and Markus Kaltenhauser, head of engineering.

The fatigue life test of the bellows was also successfully completed. Kompaflex has the capacity to produce a multi-ply rectangular construction of bellows without welding seams in the corner area, fulfilling ITER's requirement for very short building length, enormous movements in combination with a certain number of cycles, and low spring rates. A rectangular bellows with a very short convoluted length was tested for an axial movement range of 136 mm and the requested number of 500 cycles was fulfilled without any damage.

After completion of the design work on the bellows end connections, the Final Design Review for the rectangular bellows is scheduled for April 2015. The signature of the Procurement Arrangement will follow.

上一篇:Europe signs contracts for blanket first wall prototypes下一篇:Disruption mitigation team reviews progress

推荐阅读
又一核电机组开工!
又一核电机组开工!
4月26日11时56分,国家电投广东廉江核电项目一期工程2
12个!又一“核电大省”披露重点项目名单
12个!又一“核电大省”披露重点项目名单
“核电大省”广东日前发布广东省2024年重点建设项目计
刚刚!又一台核电机组首次并网成功
刚刚!又一台核电机组首次并网成功
4月9日20时29分,中广核广西防城港核电站4号机组首次
中国广核披露一季度发电量及11台核电机组建设情况!
中国广核披露一季度发电量及11台核电机组建
4月9日,中国广核披露2024年第一季度运营情况。2024年
首届核能峰会举行,核能复兴开始……了吗?
首届核能峰会举行,核能复兴开始……了吗?
3月21日,首届核能峰会在比利时首都布鲁塞尔举行,会
我国在建核电机组 26 台,保持全球第一
我国在建核电机组 26 台,保持全球第一
近年来,中国核电产业迎来了重启后的审批和建设高潮。
精彩图片
  • 又一核电机组开工!
  • 12个!又一“核电大省”披露重点项目名单
  • 刚刚!又一台核电机组首次并网成功
  • 中国广核披露一季度发电量及11台核电机组建设情况!
    关注我们
  • 微信公众号:
  • NuclearNet
  • 扫描二维码加关注

Powered by Discuz! X3.2 © 2001-2013 Comsenz Inc.

联系我们|网站声明|中国核网-核能领域第一垂直门户网站