超导生产稳步推进

发布时间:2014-10-20 14:08 原作者:Yoshihiro NABARA, ITER Japan   来自: ITER newsline

During the week of 6 October, the 12th Conductor Meeting took place in Kokura, Japan near the Wakamatsu ITER factory, where jacketing activities for ITER's toroidal field conductors and central solenoid conductors have been underway since 2010.

 

The Conductor Meeting is held semi-annually to reunite the actors involved in the procurement of conductors—from the ITER Organization, the six producing Domestic Agencies, and industrial manufacturers—for a review of progress.

 

Over 95 percent of toroidal field superconducting strand lengths and approximately 75 percent of toroidal field conductor unit lengths have been fabricated. As the procurement of toroidal field conductors nears completion, the focus of magnet activities is shifting to the next phase: the fabrication of 19 toroidal field coils (18 plus one spare). Three toroidal field conductors have been wound and heat treated in Japan and Europe.

 

Progress was also reported on central solenoid conductor procurement. Five central solenoid conductor unit lengths (approximately 10 percent of total needs) were fabricated and transferred from Japan to the USA in June 2014. These conductors will be wound for the lower module of the central solenoid coil stack (CS3L) in California.

 

The Conductor Meeting is held semi-annually to reunite the actors involved in the procurement of conductors—from the ITER Organization, the six producing Domestic Agencies, and industrial manufacturers—for a review of progress.

 

Strand and conductor production for the poloidal field coils is also steadily advancing, with 18 unit lengths of poloidal field conductor manufactured to date.

 

Arnaud Devred, head of ITER's Superconductor Systems & Auxiliaries Section, looks back with satisfaction on seven years of collaboration on magnets. "We have come a long way since the signature of the first magnet Procurement Arrangement with Japan (for the toroidal field conductor) in November 2007. As of today, more than 140 conductor unit lengths have been completed by China, Europe, Japan, Korea, Russia and the United States and the ITER Organization has cleared approximately 9,700 control points through the web-based ITER conductor database."

 

"In spite of extraordinary tough project constraints, the ITER Organization and Domestic Agency responsible officers have been able to build a strong collaborative spirit and a good mutual understanding of the technical and quality assurance/quality control requirements that have been instrumental in overcoming difficulties and ensuring progress. The Conductor Meeting has been an important and effective forum for exchanging information"

 

The next Conductor Meeting will take place in March 2015 at the CRPP fusion institute in Switzerland with the participation of the SULTAN working group for ITER conductor tests. A final conductor meeting is foreseen in September 2015 at the ITER Organization.

 

Original Title: Conductor production keeps progressing

上一篇:The European Commission launches EUROfusion下一篇:KSTAR Surpasses 10 Thousand Mark in Plasma Generation Test

推荐阅读
又一核电机组开工!
又一核电机组开工!
4月26日11时56分,国家电投广东廉江核电项目一期工程2
12个!又一“核电大省”披露重点项目名单
12个!又一“核电大省”披露重点项目名单
“核电大省”广东日前发布广东省2024年重点建设项目计
刚刚!又一台核电机组首次并网成功
刚刚!又一台核电机组首次并网成功
4月9日20时29分,中广核广西防城港核电站4号机组首次
中国广核披露一季度发电量及11台核电机组建设情况!
中国广核披露一季度发电量及11台核电机组建
4月9日,中国广核披露2024年第一季度运营情况。2024年
首届核能峰会举行,核能复兴开始……了吗?
首届核能峰会举行,核能复兴开始……了吗?
3月21日,首届核能峰会在比利时首都布鲁塞尔举行,会
我国在建核电机组 26 台,保持全球第一
我国在建核电机组 26 台,保持全球第一
近年来,中国核电产业迎来了重启后的审批和建设高潮。
精彩图片
  • 又一核电机组开工!
  • 12个!又一“核电大省”披露重点项目名单
  • 刚刚!又一台核电机组首次并网成功
  • 中国广核披露一季度发电量及11台核电机组建设情况!
    关注我们
  • 微信公众号:
  • NuclearNet
  • 扫描二维码加关注

Powered by Discuz! X3.2 © 2001-2013 Comsenz Inc.

联系我们|网站声明|中国核网-核能领域第一垂直门户网站