文章

A floor to support 400,000 tons

发布时间:2014-8-29 09:22 原作者:Krista Dulon   来自: ITER newsline

To pour the last 576 square metres of the Tokamak Complex basemat (the B2 slab), workers began manning two concrete pumps before dawn on 27 August 2014.


"Relief," "pride," "a sense of satisfaction"... these words were heard on the afternoon of 27 August as the last segment of the Tokamak Complex basemat (the B2 slab) was successfully poured.

Work that began at 5:50 a.m. on the perfectly circular segment that will support the weight of the ITER Tokamak ended 12 hours later at 6:00 p.m.

Late in the afternoon, some 100 people gathered in the Tokamak Pit—representatives of the ITER Organization; the European Domestic Agency, Fusion for Energy (F4E); F4E service contractors Engage (detailed design and work supervision), Energhia (management support) and Apave (health, safety and legal inspection services); and the F4E construction consortium led by GTM Sud from France—to celebrate the imminent completion of the works.

ITER Director-General Osamu Motojima had the honour of putting the final, symbolic touch to the day's work. After smoothing the concrete surface with a trowel, he stopped to thank the workers for their hard work and dedication over the past months. He then turned to include the representatives of the organizations that had collaborated in the successful finalization of the B2 slab: "I congratulate all of you on this historic milestone—you have played an important role in the realization of ITER. The completion of concrete pouring on the B2 slab today represents a huge step forward." 


The finalization of the B2 slab (15 segments, 14,000 m³ of concrete, 3,600 tons of rebar) took eight months. Hundreds of people contributed to the different aspects of its realization, including design, procurement, scheduling, quality, finance and construction.


The B2 slab will support some 400,000 tons of building and equipment, including the 23,000-ton ITER Tokamak. It's a "floating" foundation—installed on seismic columns, it has a capacity for lateral movement of up to 10 cm in any direction (a gap of approximately 1.5 metres separates the B2 slab from the surrounding retaining walls). The 1.5-metre-thick slab will serve as the first basement level of the Diagnostic, Tokamak and Tritium buildings; five large drain tanks, supports for the base of the cryostat (the concrete crown), and the building walls will be positioned directly on it.

"Today is a terrific day for the ITER Project," said Tim Watson, head of ITER's Buildings & Site Infrastructure Directorate. "The completion of the B2 slab was the last step in creating the ground support structure and anti-seismic foundations for the ITER Tokamak. Now, we can look forward to seeing the Tokamak Complex walls rise."

Concrete pouring for the 9,300 m² B2 slab began in December 2013. It took three pours to realize the Diagnostic Building basemat at the south side of the Tokamak Pit, and another three to realize the Tritium Building foundation at the opposite end. Both were relatively straightforward compared to the central part of the basemat, where orthoradial (circular) and orthogonal (right-angled) rebar arrangements interface. Following months of exchanges with the French Nuclear Safety Authority (ASN) and its technical experts at the Institute for Radioprotection and Nuclear Safety (IRSN), the hold point on this part of the slab was lifted and pouring operations were allowed to proceed.

"Today's milestone demonstrates the project's capability to respect the required safety processes and advance systems integration, efforts which resulted in the release of the hold point by the ASN," emphasized Director-General Motojima.


"With the completion of the B2 slab, a new chapter opens in the history of our project," said ITER Director-General Motojima. "In September, construction of the Tokamak Complex will begin in earnest. You have built the floor; now come the walls, then the roof, and after that the machine itself..."


"Miguel Curtido is F4E's technical responsible officer for the B2 slab: "Once we were given the green light, we began pouring the same day. We managed to keep a strong rhythm despite peaks in temperature and vacation schedules that made the pour days harder to schedule. We worked double shifts, on Saturday and—on three occasions—we poured concrete at night. The fact that we were able to realize nine segments in seven weeks is testimony to the incredible dedication of the entire team."

"We kept to an ambitious schedule," adds Ben Slee, deputy head of Site, Buildings and Power Supplies at Fusion for Energy, "but at all times our first priority was quality and safety—these were not jeopardized at any moment. Today we have to thank not only those working on the construction site but also the hundreds of others who have been involved since the preparation and signature of the contract, within the different organizations, and who made this construction possible in terms of design, procurement, scheduling, quality, finance, etc."

The B2 slab concludes work started four years ago to create a ground support structure for the Tokamak Complex that will protect the buildings and equipment in the case of a seismic event. A 17-metre-deep, 90 x 130 metre area was excavated and a ground-level basemat, retaining walls, and 493 seismic columns and pads were progressively installed. All of these works were carried out by the F4E construction consortium led by GTM Sud. (The anti-seismic bearings were installed by Nuvia Traveaux Speciaux which, like GTM, is part of the French group Vinci.)

There now remain some procedural elements to conclude for the B2 slab (inspections, documentation); also, over the next few weeks GTM will be removing formwork and material from the worksite. "But today's milestone is key," says Miguel, "because it will allow the Tokamak Complex building consortium, VFR, to soon take possession of the entire B2 slab."

The VFR consortium has already started to install formwork to frame out the lower walls of the Diagnostic Building. Next month, it will start to install five large cranes—including an 80-metre crane at the very centre of the Tokamak Pit—to transport building materials from storage areas at ground level to the B2 slab surface. 

The next phase of ITER construction is beginning. The number of workers on site will significantly increase in the near future as work begins on the walls of the Tokamak Complex and the first 60-metre-tall pillars are set into place for the adjacent Assembly Building.

上一篇:Contract signed in Europe for diagnostics integration下一篇:CEA-ITER facility to test the assembly of magnet components

推荐阅读
又一核电机组开工!
又一核电机组开工!
4月26日11时56分,国家电投广东廉江核电项目一期工程2
12个!又一“核电大省”披露重点项目名单
12个!又一“核电大省”披露重点项目名单
“核电大省”广东日前发布广东省2024年重点建设项目计
刚刚!又一台核电机组首次并网成功
刚刚!又一台核电机组首次并网成功
4月9日20时29分,中广核广西防城港核电站4号机组首次
中国广核披露一季度发电量及11台核电机组建设情况!
中国广核披露一季度发电量及11台核电机组建
4月9日,中国广核披露2024年第一季度运营情况。2024年
首届核能峰会举行,核能复兴开始……了吗?
首届核能峰会举行,核能复兴开始……了吗?
3月21日,首届核能峰会在比利时首都布鲁塞尔举行,会
我国在建核电机组 26 台,保持全球第一
我国在建核电机组 26 台,保持全球第一
近年来,中国核电产业迎来了重启后的审批和建设高潮。
精彩图片
  • 又一核电机组开工!
  • 12个!又一“核电大省”披露重点项目名单
  • 刚刚!又一台核电机组首次并网成功
  • 中国广核披露一季度发电量及11台核电机组建设情况!
    关注我们
  • 微信公众号:
  • NuclearNet
  • 扫描二维码加关注

Powered by Discuz! X3.2 © 2001-2013 Comsenz Inc.

联系我们|网站声明|中国核网-核能领域第一垂直门户网站