文章

NIF能力得到提升

发布时间:2014-10-9 11:03    来自: Lawrence Livermore National Laboratory

Planning, scheduling, and efficiency changes designed to enhance NIF’s productivity have resulted in a continuous increase in the number of experiments NIF was able to conduct during Fiscal Year 2014, which ended Sept. 30.

NIF completed a weekly average of 6.9 laser shots with targets in the fourth quarter of FY 2014—more than double the rate of 2.8 shots per week in the first quarter of the year. The quarter ended with a two-week test of complex high-shot-rate operations, with nine shots conducted each week. For the year, the NIF Team conducted a total of 191 target experiments against an original planned total of 150.

The shot rate growth is due largely to the fact that “NIF is spending more time shooting,” said NIF User Facility Manager Doug Larson. NIF adopted a model used successfully at the OMEGA Laser Facility at the University of Rochester, where the facility clearly separates “shot mode” from “maintenance mode.” NIF’s implementation of this model involved shooting around the clock for five straight days each week, and then doing 48 hours of maintenance. This allowed experiments to be conducted on a more continuous basis, with less startup time and fewer interruptions compared with doing a combination of shots and maintenance each day.

Sean Bradley, Paul Bonifacio, Eric Downing and Nick St. Hilaire of the NIF Transport & Handling Team remove the Final Optics Damage Inspection (FODI) instrument from its position in the NIF Target Bay to protect its camera and electronics from neutron radiation damage during a high-yield shot. Thanks to new lifting controls and devices and crew experience, this once complex operation is now routinely performed in a fraction of the time it once took.

Another change that resulted in more shots was the initiation of a fast-turnaround operations model based on the Formula One race car pit-crew model, developed by the NIF Team early this year to improve shot turnaround efficiency and enable a new scheduling paradigm (seeNIF’s “Formula One” Model Receives Operational Excellence Award).

A third initiative to boost shot production was the introduction of “mini-campaigns” designed to minimize facility changes while optimizing data return. In late June, for example, the NIF Team conducted a zirconium backlighter mini-campaign by firing four full-system shots in 20 hours—a NIF record. The mini-campaign “was an opportunity to test new operations and scheduling concepts which will help us transform the NIF into a user facility that will take full advantage of its potential,” said NIF&PS Principal Associate Director Jeff Wisoff.

Then there was the introduction of warm (room-temperature) “subscale” NIF targets in July. The size of both the target capsule and hohlraum are scaled to about 80 percent the size of an ignition target. These targets, used in tuning experiments, require less laser energy, have less optics impact, and are faster to field than their full-scale cryogenic counterparts, providing a more efficient tuning platform. Ten warm subscale target shots were successfully conducted in a mini-campaign during the week of Sept. 19.

These improvements and others were recommended by a Congressionally-mandated 120-day study to find ways of increasing the NIF shot rate over three years at a constant annual funding level. A national team of NIF collaborators and sponsors led by Larson and then-NIF Director Jeff Atherton made organizational, engineering, scheduling, and experimental configuration recommendations to enhance NIF’s shot availability. Among the recommendations, which are being implemented in close collaboration with NIF’s users, were increasing the number of hours dedicated to shots during shot weeks from about 80 to 120; increasing the number of shot weeks per year from 38 to 44; and reducing shot cycle time. By engaging the NIF user community as well as NIF’s sponsors in the effort, Wisoff said, the study will further the ultimate goal of transforming NIF into a world-class user facility.

A tritium-filled symmetry capsule (symcap) target assembled and aligned on the NIF cryogenic target positioner (Cryo TarPos).

The 120-day study also recommended alternating the use of the cryogenic target positioner (Cryo TarPos) and target positioner (TarPos) from one shot to the next, a process that was successfully tested in September and resulted in the completion of nine shots a week during two successive weeks. When one positioner is warmed up, the target is installed and prepared for the shot while the shot cycle is proceeding on the cold target with the other positioner. The change removed the long target installation and preparation sequence from the critical path of the shot schedule, reducing the typical 20-hour shot cycle for cryogenic shots to less than 12.5 hours.

Allen Riddle (left), Adam Heal, and Dave Trummer discuss air filters and other particulars for installing upgraded cryo pumps on the NIF target positioner (TarPos). The new cryo pumps allow parallel operations on the TarPos and Cryo TarPos, significantly speeding up cryogenic shots.

The first week was dedicated to inertial confinement fusion (ICF) shots. The shortest cryogenic shot cycle observed was less than 10 hours. Six 192-beam cryogenic shots were fired in 75 hours, including a layered deuterium-tritium target. These were followed by three room-temperature 192-beam ICF shots; the average shot time was 12 hours and 46 minutes. The shot times included final optics damage inspections, wavelength changes, and reconfigurations. The second week was dedicated to the high energy density program; average shot time was 12 hours and 50 minutes.

The two high-tempo weeks also demonstrated the significant advantage of managing larger shot time blocks among the participants to achieve an overall efficiency improvement.

Orginial Title: Operational Improvements Boost NIF’s Productivity

上一篇:LLNL在10拍瓦激光项目中居于核心地位下一篇:马克赫尔曼-NIF新掌门人

推荐阅读
中核二三领导班子调整
中核二三领导班子调整
8月22日,中核二三召开干部任职宣布大会,公司党委书
辛安核电项目有进展
辛安核电项目有进展
8月15日,烟台市人民政府网站发布《山东海阳辛安核电
定了!中国华能迎新任总经理!
定了!中国华能迎新任总经理!
2024年8月19日,中国华能集团有限公司召开领导班子(
国常会核准5个核电项目,合计11台机组,拉动千亿级投资!
国常会核准5个核电项目,合计11台机组,拉
国务院总理李强8月19日主持召开国务院常务会议,决定
中核集团人事密集调整!涉及江苏核电等!
中核集团人事密集调整!涉及江苏核电等!
宋克祥任中核医疗产业管理有限公司总经理、党委副书记
中广核新能源江西分公司原总经理邓东被查!
中广核新能源江西分公司原总经理邓东被查!
8月12日,“廉洁南昌”发布消息称,中国广核新能源控
精彩图片
  • 中核二三领导班子调整
  • 辛安核电项目有进展
  • 定了!中国华能迎新任总经理!
  • 国常会核准5个核电项目,合计11台机组,拉动千亿级投资!
    关注我们
  • 微信公众号:
  • NuclearNet
  • 扫描二维码加关注

Powered by Discuz! X3.2 © 2001-2013 Comsenz Inc.

联系我们|网站声明|中国核网-核能领域第一垂直门户网站