超导生产稳步推进

发布时间:2014-10-20 14:08 原作者:Yoshihiro NABARA, ITER Japan   来自: ITER newsline

During the week of 6 October, the 12th Conductor Meeting took place in Kokura, Japan near the Wakamatsu ITER factory, where jacketing activities for ITER's toroidal field conductors and central solenoid conductors have been underway since 2010.

 

The Conductor Meeting is held semi-annually to reunite the actors involved in the procurement of conductors—from the ITER Organization, the six producing Domestic Agencies, and industrial manufacturers—for a review of progress.

 

Over 95 percent of toroidal field superconducting strand lengths and approximately 75 percent of toroidal field conductor unit lengths have been fabricated. As the procurement of toroidal field conductors nears completion, the focus of magnet activities is shifting to the next phase: the fabrication of 19 toroidal field coils (18 plus one spare). Three toroidal field conductors have been wound and heat treated in Japan and Europe.

 

Progress was also reported on central solenoid conductor procurement. Five central solenoid conductor unit lengths (approximately 10 percent of total needs) were fabricated and transferred from Japan to the USA in June 2014. These conductors will be wound for the lower module of the central solenoid coil stack (CS3L) in California.

 

The Conductor Meeting is held semi-annually to reunite the actors involved in the procurement of conductors—from the ITER Organization, the six producing Domestic Agencies, and industrial manufacturers—for a review of progress.

 

Strand and conductor production for the poloidal field coils is also steadily advancing, with 18 unit lengths of poloidal field conductor manufactured to date.

 

Arnaud Devred, head of ITER's Superconductor Systems & Auxiliaries Section, looks back with satisfaction on seven years of collaboration on magnets. "We have come a long way since the signature of the first magnet Procurement Arrangement with Japan (for the toroidal field conductor) in November 2007. As of today, more than 140 conductor unit lengths have been completed by China, Europe, Japan, Korea, Russia and the United States and the ITER Organization has cleared approximately 9,700 control points through the web-based ITER conductor database."

 

"In spite of extraordinary tough project constraints, the ITER Organization and Domestic Agency responsible officers have been able to build a strong collaborative spirit and a good mutual understanding of the technical and quality assurance/quality control requirements that have been instrumental in overcoming difficulties and ensuring progress. The Conductor Meeting has been an important and effective forum for exchanging information"

 

The next Conductor Meeting will take place in March 2015 at the CRPP fusion institute in Switzerland with the participation of the SULTAN working group for ITER conductor tests. A final conductor meeting is foreseen in September 2015 at the ITER Organization.

 

Original Title: Conductor production keeps progressing

上一篇:The European Commission launches EUROfusion下一篇:KSTAR Surpasses 10 Thousand Mark in Plasma Generation Test

推荐阅读
中核二三领导班子调整
中核二三领导班子调整
8月22日,中核二三召开干部任职宣布大会,公司党委书
辛安核电项目有进展
辛安核电项目有进展
8月15日,烟台市人民政府网站发布《山东海阳辛安核电
定了!中国华能迎新任总经理!
定了!中国华能迎新任总经理!
2024年8月19日,中国华能集团有限公司召开领导班子(
国常会核准5个核电项目,合计11台机组,拉动千亿级投资!
国常会核准5个核电项目,合计11台机组,拉
国务院总理李强8月19日主持召开国务院常务会议,决定
中核集团人事密集调整!涉及江苏核电等!
中核集团人事密集调整!涉及江苏核电等!
宋克祥任中核医疗产业管理有限公司总经理、党委副书记
中广核新能源江西分公司原总经理邓东被查!
中广核新能源江西分公司原总经理邓东被查!
8月12日,“廉洁南昌”发布消息称,中国广核新能源控
精彩图片
  • 中核二三领导班子调整
  • 辛安核电项目有进展
  • 定了!中国华能迎新任总经理!
  • 国常会核准5个核电项目,合计11台机组,拉动千亿级投资!
    关注我们
  • 微信公众号:
  • NuclearNet
  • 扫描二维码加关注

Powered by Discuz! X3.2 © 2001-2013 Comsenz Inc.

联系我们|网站声明|中国核网-核能领域第一垂直门户网站