ITER极向场交直流转换器设计评估结束

发布时间:2014-10-24 14:04 原作者:Inyoung Suh, Coil Power Supply Section   来自: ITER newsline

The Final Design Review for the poloidal field AC/DC converter was successfully held in Beijing, China on 23-25 September. In advance of the meeting—in addition to the routine duties of reviewing design documentation submitted by the Chinese Domestic Agency and its suppliers—the review panel headed by chair Ivone Benfatto of ITER's Electrical Engineering Division faced the difficult challenge of finding flights to China in the context of a major Air France strike. Fortunately, all participants were able to arrive on time and the meeting was completed according to schedule.

 

According to a Procurement Arrangement signed with the ITER Organization in 2011, the Chinese Domestic Agency is responsible for the procurement of the 14 poloidal field AC/DC converter units that will provide reliable, controlled DC power to the ITER poloidal field magnetic coils and dummy load for site testing.

 

During the meeting, the Chinese Domestic Agency and its suppliers presented their work on the final design and testing of the poloidal field AC/DC converter system and its main components such as converter transformer and converter modules. Interface requirements, key electrical and mechanical design, and Factory Acceptance Test (FAT) and Site Acceptance Test (SAT) procedures were carefully examined by the review panel members and experts.

 

The main supplier ASIPP (the Institute of Plasma Physics, Chinese Academy of Sciences) showcased their one-of-a-kind test platform which was designed and constructed to test the ITER poloidal field converter system at various rated operation and fault conditions to verify their design. Test results of the full-scale prototype using the test platform were essential in the validation of the ASIPP final design.

 

The ITER Organization and Chinese Domestic Agency participants concluded the Final Design Review with a debriefing session to discuss the results of chit categorization and future actions. There were no critical chits and the review panel was confident that procurement can now advance to the next manufacturing review stage on schedule.

 

The meeting ended in a cooperative spirit with a remark by Peng Fu, chief engineer and ITER Project manager at ASIPP, who said, "For us chits are not just issues to be resolved, they are good proposals to improve the product and prototype design."

The Final Design Review for the poloidal field AC/DC converter was successfully held in Beijing, China on 23-25 September.

Original TtitleReview propels poloidal field AC/DC converters to next stage

上一篇:Lockheed Martin's fusion goals meet skepticism下一篇:ITER实验包层模块项目取得显著进展

推荐阅读
中核二三领导班子调整
中核二三领导班子调整
8月22日,中核二三召开干部任职宣布大会,公司党委书
辛安核电项目有进展
辛安核电项目有进展
8月15日,烟台市人民政府网站发布《山东海阳辛安核电
定了!中国华能迎新任总经理!
定了!中国华能迎新任总经理!
2024年8月19日,中国华能集团有限公司召开领导班子(
国常会核准5个核电项目,合计11台机组,拉动千亿级投资!
国常会核准5个核电项目,合计11台机组,拉
国务院总理李强8月19日主持召开国务院常务会议,决定
中核集团人事密集调整!涉及江苏核电等!
中核集团人事密集调整!涉及江苏核电等!
宋克祥任中核医疗产业管理有限公司总经理、党委副书记
中广核新能源江西分公司原总经理邓东被查!
中广核新能源江西分公司原总经理邓东被查!
8月12日,“廉洁南昌”发布消息称,中国广核新能源控
精彩图片
  • 中核二三领导班子调整
  • 辛安核电项目有进展
  • 定了!中国华能迎新任总经理!
  • 国常会核准5个核电项目,合计11台机组,拉动千亿级投资!
    关注我们
  • 微信公众号:
  • NuclearNet
  • 扫描二维码加关注

Powered by Discuz! X3.2 © 2001-2013 Comsenz Inc.

联系我们|网站声明|中国核网-核能领域第一垂直门户网站