Eight months after the "first pour" of the B2 slab, workers are preparing to realize the final segment. The last pour is scheduled for end August 2014. Building begins in 2014 on the Tokamak
Complex, the 360,000-ton edifice that will house the ITER Tokamak and
supporting diagnostic and tritium systems.
Eighty metres tall, 120 metres long and 80
metres wide, the Tokamak Complex will dominate the ITER scientific installation
when it is completed in 2016. Its construction will require 16,000 tons of
rebar, 150,000 m³ of concrete and 7,500 tons of steel for the building
structures. A dedicated batching plant on site, with two mixing machines and
eight holding tanks, will supply the concrete in order to limit the amount of
construction vehicles travelling on the roads in the area of the ITER
construction site.
The Tokamak Complex will be built in a 90 x
130 metre area on the ITER platform, the Seismic Pit, which was excavated and
reinforced with a ground support structure between 2010 and 2012. A 1.5-metre basemat
and thick retaining walls are now in place to protect the future buildings and
their equipment from ground motion in the case of an earthquake.
On the level surface of the Seismic Pit
basemat, 493 columns were cast and topped with 20 cm-thick anti-seismic bearing
made of alternate layers of metal and rubber. With a capacity for lateral
movement of 10 cm, these bearings—which will support the foundation of the
Tokamak Complex—are capable of filtering and absorbing the accelerations linked
to ground motion.
The last step before Tokamak Complex
construction was the realization of 1.5-metre-thick reinforced basemat, the B2
slab. Propping and reinforcement works for the B2 slab were carried out in
2013. The basemat was poured in 15 segments over a nine-month period, from
December 2013 to August 2014.
With the B2 basemat slab in
place, construction can begin on the buildings of the Tokamak Complex.
|